Why is Punatsangchhu-I delayed?
The short version: the mountain would not hold. A slow toe-slide in 2013 on the right bank above the dam pit revealed rock far weaker than the surveys had read, and the active mountain-building that raised the Himalaya turned out to be still at work directly beneath the site. Since then the project’s history has been told in geology — shear zones, slope stabilisation, re-engineering — rather than in turbines.
The cost of the delay compounds in every direction: a budget roughly tripled, eighteen years without a unit generated — longer than China took to build a dam thirteen times larger — and an entire cohort of engineers who have spent most of a career on one unfinished plant (Paradox #3).
The full story of both dams — including why the “successful” sister, PHPA-II, ended up carrying 78% of the nation’s audit irregularities — is in The Punatsangchhu Problem, and what it means for the ten further projects Bhutan plans is the harder question underneath it.