The Bhutan We Think We Know

Bht 99

USD 2.4bn

realised value transfer to India · 1985–2026

The Four Faces of One Transfer

Plus another USD 4bn of forward present value through 2060. Each leak is defensible in isolation. The peg makes the sum invisible.

Why no one sees it

The closed loop with India is not symmetrical

Bhutan sends power, currency parity, hydropower revenue, and below-cost electricity into the relationship with India. India sends fuel, capital, grants, and the rupee peg back. The four flows below are the parts of Bhutan’s contribution that are not netted in the ledger — because the books are kept in ngultrum, and ngultrum always balance.

The dollars do not.

BHUTANSOURCEINDIARECIPIENTUSD 50–80M / YRPPA FX lossINR-denominated PPAs, no USD-reference clauseUSD 10M / YR (FOREGONE)Seigniorage never claimed52 years of rupee circulation, no CMA-equivalent compensationUSD 281M / YRHV1 below export paritySold to 23 industrials at Nu 1.60/kWh — below Tala exportUSD 33–44M / YR (CASH LOSS)Lean-season buy high, sell lowImports lean power at Nu 4–6/kWh, resells at Nu 1.60Total ongoing flow ≈ USD 375M / year · Cumulative realised ≈ USD 2.4bn since 1985

Each leak is large enough to matter — between USD 10M and USD 281M per year — but small enough to fit inside the noise of bilateral financial flows. Each is justified by its own rationale. The sum is the issue.

The mechanism

Why ngultrum accounting makes this invisible

A ngultrum and a rupee are one-to-one by statute since 1974. Every cross-border ngultrum receipt is automatically a rupee receipt. The current account balances in ngultrum; the dollars are never required to balance because the dollar leg is never explicitly recorded.

When the rupee depreciates against the dollar by 4–5% per year — as it has done, with brief reversals, every year since the Tala PPA was signed in 1985 — the Bhutanese ngultrum receipt is fully intact on the RMA balance sheet. The USD purchasing power it represents has fallen.

≈ 85%

cumulative loss in INR/USD exchange rate since Chhukha COD in 1986

The peg works as designed: price stability, seamless cross-border trade. It also works as a structural blindfold. The country cannot see the four flows below because they do not produce ngultrum imbalances — they produce dollar imbalances, and the dollar is not measured.

First face · Paradox #62

The PPA FX loss the peg makes invisible

Every Bhutanese hydropower Power Purchase Agreement with India is denominated in Indian rupees with no USD-reference clause. Since Chhukha’s commissioning in 1986, the rupee has lost roughly 85% of its USD value. The PPAs continue at fixed-tariff structures negotiated decades ago.

USD 50–80M

current annual FX-loss flow

USD 1.85bn

realised loss since CODs to 2024

USD 4–5bn

forward PV through 2060

The peg keeps the ledger in ngultrum. The dollars depreciate quietly off-balance-sheet.

The forward number gets worse, not better. The 2024–2060 pipeline includes Sankosh, Kuri-Gongri, Dorjilung — all currently being negotiated under the same INR-denominated PPA template that produced the past loss. Each new PPA signed without a USD reference locks in the next forty years of the same mechanism.

Second face · Paradox #61

The seigniorage Bhutan never claimed

The Common Monetary Area between South Africa, Lesotho, Eswatini, and Namibia includes a formula: the South African Reserve Bank compensates the smaller states annually for rand circulating in their economies. The formula is 2/3 × SA 10-year government stock yield × rand-in-circulation.

In FY 2023/24 that payment totalled R1.4 billion across the three states. It is not a gift. It is the standard compensation for foregoing one’s own currency.

Nu 0

equivalent annual compensation India pays Bhutan for INR circulating in Bhutan, after 52 years of currency-sharing

A mid-scenario application of the CMA formula to Bhutan would be roughly Nu 855M / year — about USD 10M. Apply it retroactively across 52 years of unclaimed seigniorage and the cumulative undiscounted figure is USD 520M+.

This is a negotiation-table number. India does not owe what was never asked for. But the precedent in the CMA establishes that the smaller state in a currency-sharing arrangement has a claim — and that claim is currently zero only because Bhutan has not claimed.

Third face · Paradox #51

HV1 industrial tariff below export parity

Bhutan sells electricity to its 23 largest HV1 industrial customers — sovereign Bitcoin mining, cement, ferro-alloy — at Nu 1.60/kWh.

That is below the cheapest export PPA (Tala, Rs 1.98/kWh) and roughly one-third of the PHPA-II reference tariff (Rs 5.10/kWh).

Nu 1.60

HV1 industrial · per kWh

Nu 1.98

Tala export PPA · per kWh

Nu 5.10

PHPA-II reference · per kWh

Foregone export-equivalent revenue: roughly USD 281M / year. The 2026 proposed +75% revision (to Nu 2.80) narrows the gap but does not close it.

The structural argument for the low tariff is industrial competitiveness. The structural cost is that the country sells its single largest export to 23 domestic customers at a price below what it sells the same kWh to India. The asymmetry is one direction.

Fourth face · Paradox #63

Lean-season buy high, sell low

Between December and April Bhutan’s rivers run low. BPC imports electricity from the Indian Energy Exchange at Nu 4–6/kWh. It then resells that imported power to the same HV1 industrials at Nu 1.60/kWh — the price set decades ago.

The cash loss — not opportunity cost, actual cash — is USD 33–44M per year.

This is the cleanest case of the four. Bhutan buys power expensive, sells it cheap, and the gap is paid out of the BPC balance sheet. It is a direct subsidy, paid in cash, four months of every year, from the Bhutanese consumer’s electricity bill to the HV1 industrial.

USD 60–80M

projected annual cash loss by 2028 if neither tariff nor pumped-storage timeline moves

The structural fix is pumped-storage hydropower — generation that can be shifted between months. The first such project at scale is still on the planning shelf.

The total

One direction. Four mechanisms. No ledger entry.

USD 375M

current ongoing flow per year

USD 2.4bn

realised cumulative cost · 1985–2026

USD 4bn+

forward present value to 2060

The cost is the missing version of Bhutan’s second-order infrastructure: the chronic-care system not built, the geological inventory not completed, the diaspora-engagement framework not established, the credit-conversion architecture missing.

The fix

Dual-ledger accounting

The first step toward fixing any of the four leaks is dual-ledger accounting — every material ngultrum flow with India should carry a parallel USD-equivalent line in RMA and Ministry of Finance reports.

Until that change, the question of should Bhutan claim seigniorage / renegotiate PPAs / raise HV1 tariffs / build pumped storage cannot be debated on the basis of evidence the country’s own financial-reporting system produces. The numbers do not appear in any internal report because the system was designed for a one-to-one peg that does not require dual measurement.

Step 1

Dual-ledger: RMA + MoF reports show both ngultrum and USD-equivalent for every material India-side flow

Step 2

Pipeline PPAs (Sankosh, Kuri-Gongri, Dorjilung) renegotiated with USD-reference clauses pre-COD

Step 3

Seigniorage claim formally tabled in bilateral economic negotiations

Step 4

HV1 tariff aligned to PHPA-II reference over a defined transition window

Step 5

Pumped-storage hydropower projects fast-tracked; lean-season import dependency reduced

None of the five is novel. Each is the work of a specific ministry. The reason none has happened is that no internal report shows the cumulative cost of not doing them — because the books are still kept in ngultrum.